Complete Kitchen, Bath, Living Area, and Entry Finishes and Fixtures rehab of over 1,200 Apartment Units. Schedule, schedule, schedule. This project allowed us to display how to effectively manage 30 crews turning over 5-6 units per week, every week, for 50 straight weeks through Process, Pre-Planning, and Schedule. BIC is proud to have devised a system to effectively manage and turn over high volume, high frequency rehabs throughout 4 separate locations.
- Managed 30 Crews across 4 Locations
- Turned over 5 Units at a time over a 5-7 day Turn Schedule per Unit
- Units consisted of New Bathrooms and New Kitchens
- Pre-Packaged Inventory Deliveries specific per unit type were created
- This project was all about schedule and maintaining quality control